PMP Practice Question 1088 - Process
A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members. What should the project manager do next?
- ✓ Correct A.Review lessons learned from similar projects with the team.
- B.Explain the higher-level objectives to be assigned to the team.
- C.Review the budget with the team for the needed resources.
- D.Assign critical tasks to the most experienced team members.
Correct answer: A
Explanation
When using a highly adaptive approach with specialized experts and seeking practical plans with high team buy-in, the project manager should review lessons learned from similar projects with the team. Collaborative review of past experience builds shared understanding and informed planning. Explaining higher-level objectives (B) provides direction but not practical planning insight. Reviewing the budget (C) addresses resources, not planning approach. Assigning critical tasks to experienced members (D) is execution, not planning.
Practice the full 2,250-question bank
This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.
Start free