A project team member tells the project lead that expecting a similar delivery output for every day of the sprint is not realistic. The project lead reports this to the project management office (PMO). What should the project lead do?

  • A.Discuss the issue with the product owner.
  • ✓ Correct B.Discuss this with the project team in the next sprint retrospective meeting.
  • C.Discuss this with the project team in the next sprint planning meeting.
  • D.Discuss this with the PMO manager.

Correct answer: B

Explanation

When a team member tells the project lead that expecting uniform daily delivery output is unrealistic, the project lead should discuss this with the project team in the next sprint retrospective meeting. Retrospectives are designed for process improvement discussions. Discussing with the product owner (A) addresses product, not process. Discussing in sprint planning (C) focuses on upcoming work. Discussing with the PMO manager (D) escalates without team input.

Practice the full 2,250-question bank

This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.

Start free