PMP Practice Question 2226
At the end of quarter 2, a project shows: PV = $150,000, EV = $165,000, AC = $160,000. Which statement is correct?
- ✓ Correct A.Cost variance is $5,000 favorable and schedule variance is $15,000 favorable.
- B.Cost variance is -$5,000 unfavorable and schedule variance is $15,000 favorable.
- C.Cost variance is $10,000 favorable and schedule variance is -$15,000 unfavorable.
- D.Cost variance is -$10,000 unfavorable and schedule variance is $5,000 favorable.
Correct answer: A
Explanation
CV = EV - AC = $165,000 - $160,000 = $5,000 (positive = favorable/under budget). SV = EV - PV = $165,000 - $150,000 = $15,000 (positive = favorable/ahead of schedule). The project is performing well on both cost and schedule dimensions.
Practice the full 2,250-question bank
This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.
Start free