PMP Practice Question 676 - People

PeopleGovernanceStakeholdersAgile

A company recently adopted agile to develop innovation projects. The project manager is experiencing problems with some team members who consider some agile ceremonies to be unnecessary. What should the project manager have done before the beginning of the project?

  • A.Discussed with the product owner and requested assistance by requiring the adoption of agile ceremonies.
  • ✓ Correct B.Prepared an inception deck and clearly explained the purpose of agile ceremonies and their benefits to the project.
  • C.Discussed with the project sponsor about convincing the team to adopt the agile ceremonies as part of their routine.
  • D.Conducted a survey to determine if the team was willing to adopt agile ceremonies on the current project.

Correct answer: B

Explanation

Before starting an agile project, the PM should ensure all team members understand the value and purpose of agile ceremonies. Preparing an inception deck and explaining ceremony benefits aligns team expectations and secures buy-in. Agile ceremonies foster collaboration, transparency, and continuous improvement—essential for innovation project success.