PMP Practice Question 1201 - Process
A project is on schedule. However, during a site visit, a project manager notices that the contractor's productivity is low. What should the project manager do?
- A.Assess the opportunity to deliver the project ahead of schedule and introduce a reward system.
- B.Update the project schedule to align with the contractor ' s productivity.
- ✓ Correct C.Discuss the need to increase productivity with the contractor.
- D.Plan the close-out activities since the project is on schedule.
Correct answer: C
Explanation
The correct answer is C. Discuss the need to increase productivity with the contractor. Schedule management requires proactive monitoring and timely corrective actions. The PM should analyze schedule impacts, evaluate options, and implement appropriate responses to keep the project on track.
Practice the full 2,250-question bank
This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.
Start free