PMP Practice Question 1201 - Process

ProcessGovernanceProject WorkGeneral

A project is on schedule. However, during a site visit, a project manager notices that the contractor's productivity is low. What should the project manager do?

  • A.Assess the opportunity to deliver the project ahead of schedule and introduce a reward system.
  • B.Update the project schedule to align with the contractor ' s productivity.
  • ✓ Correct C.Discuss the need to increase productivity with the contractor.
  • D.Plan the close-out activities since the project is on schedule.

Correct answer: C

Explanation

The correct answer is C. Discuss the need to increase productivity with the contractor. Schedule management requires proactive monitoring and timely corrective actions. The PM should analyze schedule impacts, evaluate options, and implement appropriate responses to keep the project on track.