A project manager is working in a regulated industry. The minimum viable product (MVP) for the launch has been defined. The project manager learns that the regulatory body requires a prototype for inspection before the product can be launched; however, the prototype is not part of the MVP definition. What should the project manager do next?
- A.Reschedule the launch of the product until the team can produce a prototype for inspection as required by the compliance team.
- ✓ Correct B.Speak with the product manager to prioritize the compliance-related activities high enough in the backlog to submit a prototype to the regulatory body.
- C.Identify the missing requirements, prioritize the missing compliance work directly into the backlog, and assign the work to the team.
- D.Create an MVP that contains the scope for the prototype and that will be prioritized with the compliance team.
Correct answer: B
Explanation
The correct answer is B. Speak with the product manager to prioritize the compliance-related activities high enough in the backlog to submit a prototype to the regulatory body. Compliance and regulatory requirements must be addressed proactively. The PM should assess impacts, follow proper change management processes, and ensure the project meets all applicable standards.