PMP Practice Question 1251 - People
One phase of a project took much longer than initially anticipated. The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?
- ✓ Correct A.Organize a root cause analysis (RCA) workshop.
- B.Add more float to the overall project schedule
- C.Request additional contingency from the sponsor.
- D.Expedite the next phase to reduce slippage
Correct answer: A
Explanation
When a project phase takes much longer than anticipated and stakeholders express concern, the project manager should organize a root cause analysis (RCA) workshop. Understanding why the delay occurred enables corrective actions and prevents recurrence. Adding float to the schedule (B) masks the problem. Requesting additional contingency (C) adds buffer without addressing causes. Expediting the next phase (D) adds pressure without understanding the issue.
Practice the full 2,250-question bank
This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.
Start free