PMP Practice Question 1263 - Process

ProcessSchedulePlanningGeneral

A project manager is leading a team and wants each team member to produce their deliverables and be held accountable for the work product. What should the project manager do first?

  • A.Create a plan of action and milestones (POAM) to detail the deliverables for each project team member.
  • B.Engage with each project team member to explain the individual consequences of late delivery.
  • ✓ Correct C.Empower each project team member with ownership of a particular aspect of the project.
  • D.Establish a daily standup meeting where each project team member reports their progress.

Correct answer: C

Explanation

The correct answer is C. Empower each project team member with ownership of a particular aspect of the project. Resource management includes ensuring the team has adequate skills, capacity, and support. The PM should address resource gaps and challenges proactively to maintain project delivery.