PMP Practice Question 1563 - Process

ProcessScopeDeliveryAgile

A project manager is leading a project in which the product requirements have not been fully met due to several uncertainties about customer acceptance. What should the project manager do?

  • A.Gather a reduced number of approved requirements and add some extra features to fulfill the product specifications.
  • B.Stop all project activities until all requirements are set up front by the project sponsor and the key stakeholders.
  • C.Ask team members to research and collect data about the best features offered by similar products in the market.
  • ✓ Correct D.Gather enough requirements to produce a minimum viable product (MVP) with which to evaluate customer acceptance.

Correct answer: D

Explanation

When product requirements have not been fully met due to uncertainties about customer acceptance, the project manager should gather enough requirements to produce a minimum viable product (MVP) to evaluate customer acceptance. MVP development enables validation through actual customer feedback. Gathering reduced requirements and adding extra features (A) adds unvalidated scope. Stopping all activities until requirements are set (B) is overly rigid. Researching competitor features (C) does not address customer acceptance uncertainty.