PMP Practice Question 1551 - Business Environment
A project team has been tasked with delivering robotics to automate a manufacturing line. The technical teams are all in place and have the technical information needed to build and install the robots. What other factors should be considered when planning this project?
- ✓ Correct A.Safety and organizational culture.
- B.Financial and market conditions.
- C.Industry standards and research.
- D.Software, security, and infrastructure.
Correct answer: A
Explanation
When planning a robotics project to automate a manufacturing line where technical teams are already equipped, the other factors to consider are safety and organizational culture. Robotics introduces physical hazards and requires workforce readiness and change adoption. Financial and market conditions (B) influence business justification but not execution planning. Industry standards and research (C) are relevant but the team already has technical information. Software, security, and infrastructure (D) are technical factors already addressed.
Practice the full 2,250-question bank
This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.
Start free