PMP Practice Question 1613 - People

PeopleScheduleTeamHybrid

A geographically distributed project team has development issues between the collocated and virtual teams causing productivity to decrease. What should the project manager do to address this issue?

  • A.Obtain special expertise to advise the team members
  • B.Set up face-to-face meetings with project team members
  • ✓ Correct C.Develop protocols for resolving conflicts between team members
  • D.Force the team members to work from one location.

Correct answer: C

Explanation

When a geographically distributed team has development issues between colocated and virtual members causing decreased productivity, the project manager should develop protocols for resolving conflicts between team members. Establishing ground rules and conflict resolution standards creates common behavioral expectations across all locations. Obtaining special expertise (A) adds external help but does not address internal team dynamics. Setting up face-to-face meetings (B) may be impractical. Forcing colocation (D) may be infeasible and costly.

Practice the full 2,250-question bank

This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.

Start free