PMP Practice Question 1938 - Business Environment

Business EnvironmentGovernanceDeliveryAgile

A project management office (PMO) is following the execution of an organization's critical project. Some of the project phases are experiencing serious delays due to an international supply chain crisis. Project team members suggested revisiting the planned project phases to maintain the project's value delivery. What should the project manager do?

  • A.Develop a contingency plan and seek alternative suppliers.
  • B.Update the project schedule in response to the external crisis.
  • C.Schedule a meeting with the project sponsor to report and discuss the issue.
  • ✓ Correct D.Assess and consolidate projects phases and update the project management plan.

Correct answer: D

Explanation

When serious delays from an international supply chain crisis affect project phases and team members suggest revisiting planned phases, the project manager should assess and consolidate project phases and update the project management plan. Restructuring phases maintains value delivery. Developing a contingency plan (A) is one aspect but does not address phase restructuring. Updating the schedule alone (B) does not address phase consolidation. Meeting with the sponsor (C) informs but does not solve the problem.