PMP Practice Question 1951 - Process
A company is planning a digitization project. Which action should the project manager take first when defining the project scope?
- ✓ Correct A.Assess the current state process to define the scope of the digitization.
- B.Develop the software that will support the current state process.
- C.Redefine the current state process to scope the supporting software.
- D.Digitize the current state process exactly as defined.
Correct answer: A
Explanation
Before defining the digitization project scope, the PM should first assess the current-state process to understand existing problems, needs, and improvement opportunities. This assessment informs scope definition. Digitizing the current process as-is, redefining processes for software support, or developing software directly are all premature actions that should follow—not precede—a thorough current-state assessment.
Practice the full 2,250-question bank
This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.
Start free