PMP Practice Question 2126 - Process

ProcessGovernanceDeliveryAgile

A project team is using AI to automate testing in a continuous integration pipeline. The AI tool starts producing false positives at an increasing rate. What should the project manager do?

  • ✓ Correct A.Investigate the root cause of false positives, retrain or recalibrate the AI model, and establish quality thresholds for acceptable performance.
  • B.Ignore the false positives since they don't affect production.
  • C.Immediately remove the AI tool from the pipeline.
  • D.Continue using the AI tool and manually verify all flagged issues.

Correct answer: A

Explanation

When AI tools show degraded performance, the appropriate response is root cause investigation and corrective action, not abandonment or ignoring the issue. Retraining or recalibrating the model and setting quality thresholds ensures the tool continues to provide value.