A project team is considering using AI to automatically assign tasks to team members based on skill profiles and workload. What is the PRIMARY concern the PM should address?

  • A.Whether the AI assignments will reduce project costs.
  • B.Whether the AI can handle the volume of tasks in the project.
  • C.Whether the AI can integrate with the existing project management software.
  • ✓ Correct D.Whether team members' professional development goals and preferences are considered alongside AI's optimization criteria.

Correct answer: D

Explanation

AI-driven task assignment should consider not only efficiency but also team members' professional development goals, preferences, and well-being.