PMP Practice Question 2188 - Process
A project team discovers that a key project component has a significantly higher carbon footprint than initially estimated. The project is 60% complete. What should the PM do?
- A.Continue as planned since the project is too far along to change.
- ✓ Correct B.Raise a change request to evaluate lower-carbon alternatives for the remaining work, assess schedule and cost implications, and update the sustainability plan.
- C.Halt the project immediately until a green alternative is found.
- D.Offset the carbon through tree planting without changing the project.
Correct answer: B
Explanation
A formal change request evaluates alternatives while maintaining project governance. Even at 60% completion, there may be opportunities to reduce carbon impact.