PMP Practice Question 2188 - Process

ProcessGovernancePlanningHybrid

A project team discovers that a key project component has a significantly higher carbon footprint than initially estimated. The project is 60% complete. What should the PM do?

  • A.Continue as planned since the project is too far along to change.
  • ✓ Correct B.Raise a change request to evaluate lower-carbon alternatives for the remaining work, assess schedule and cost implications, and update the sustainability plan.
  • C.Halt the project immediately until a green alternative is found.
  • D.Offset the carbon through tree planting without changing the project.

Correct answer: B

Explanation

A formal change request evaluates alternatives while maintaining project governance. Even at 60% completion, there may be opportunities to reduce carbon impact.

Practice the full 2,250-question bank

This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.

Start free