PMP Practice Question 613 - People

PeopleFinanceProcessStakeholdersGeneral

A project manager is working on a multinational project that has more than 100 stakeholders. The project manager is concerned about the appropriate stakeholder participation and involvement level required for successful project delivery. What should the project manager do?

  • A.Communicate with the stakeholders to find a solution.
  • B.Review the issue log with the project stakeholders.
  • C.Perform a stakeholder assumption and constraint analysis.
  • ✓ Correct D.Evaluate the stakeholder engagement assessment matrix.

Correct answer: D

Explanation

When managing a multinational project with 100+ stakeholders and concerns about participation levels, the project manager should evaluate the stakeholder engagement assessment matrix. This tool documents desired vs. current engagement levels and identifies gaps. Communicating with stakeholders (A) is ongoing but not analytical. Reviewing the issue log (B) is reactive. Performing assumption and constraint analysis (C) addresses project analysis, not engagement.

Practice the full 2,250-question bank

This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.

Start free