PMP Practice Question 1026 - People
A project manager just finished a meeting to identify the main stakeholders of the project. What should the project manager do next?
- A.Monitor all stakeholders.
- ✓ Correct B.Analyze the stakeholders.
- C.Keep all stakeholders informed.
- D.Engage the stakeholders.
Correct answer: B
Explanation
After identifying the main stakeholders, the project manager should next analyze the stakeholders. Stakeholder analysis determines interest, influence, and potential impact to guide engagement strategy. Monitoring all stakeholders (A) comes later. Keeping all informed (C) is ongoing. Engaging stakeholders (D) follows analysis.