PMP Practice Question 1038 - People
A project is in the execution phase. The client was actively involved in the early stages but has been less engaged lately. A number of changes to the requirements have recently been requested. What should the project manager do next?
- A.Review the risk register to see if mitigations have already been outlined for this scenario.
- B.Review the changes and make the decision based on the project team ' s recommendations.
- ✓ Correct C.Discuss the changes with the client and jointly make the decision on how to proceed.
- D.Reject the changes and stay the original course as initially agreed with the client.
Correct answer: C
Explanation
When a client's engagement changes during project execution, maintaining open communication and collaboration is crucial. Discussing requested changes with the client ensures their needs are understood and considered. This collaborative approach aligns with PMI's emphasis on stakeholder engagement—jointly assessing impact on objectives, timeline, and budget to make informed decisions.