PMP Practice Question 126 - People
A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is below the target, and the tasks assigned are not delivered on time. Team commitment is also not at the expected level. What should the project manager do?
- A.Hire a project team leader who can influence the project team members.
- ✓ Correct B.Study and determine the appropriate leadership style suitable for the team.
- C.Apply an agile approach to help improve team performance.
- D.Schedule a meeting and communicate the performance concern to the team.
Correct answer: B
Explanation
Effective PMs must be able to shift between leadership styles based on the situation. Studying the team dynamics and determining the appropriate leadership style is essential for improving team performance and commitment. Different situations demand different approaches—from directive to collaborative to delegative—and the PM's flexibility in this regard directly impacts team motivation and project outcomes.
Practice the full 2,250-question bank
This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.
Start free