PMP Practice Question 1438 - Process

ProcessGovernancePlanningGeneral

A work package to configure new computer hardware is received, and a list of related project activities have also been identified. What should the project manager do?

  • A.Consult subject matter experts (SMEs) to review the schedule.
  • B.Define the project management plan.
  • ✓ Correct C.Estimate the resources needed for the activities.
  • D.Estimate the cost of each activity.

Correct answer: C

Explanation

When a work package for configuring new computer hardware is received along with related activities, the project manager should estimate the resources needed for the activities. Resource estimation determines what is required for execution. Consulting SMEs to review the schedule (A) focuses on timing, not resources. Defining the project management plan (B) is too broad. Estimating cost (D) comes after resource estimation.

Practice the full 2,250-question bank

This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.

Start free