A key stakeholder of a project wants to include additional work before completion. What should the project manager do?
- A.Meet with the stakeholder and explain that additional work cannot be added.
- ✓ Correct B.Request the additional work through governance.
- C.Prioritize the additional work in the backlog.
- D.Collaborate immediately with the stakeholder to complete the additional work.
Correct answer: B
Explanation
When stakeholders request additional scope, the PM should process the change request through the approved change control process. Unilateral changes bypass governance, risk scope creep, and undermine project baselines. Formal change control ensures alignment with scope, budget, and timeline while maintaining transparency and stakeholder agreement.