PMP Practice Question 1676 - People
During a discovery phase, a project manager coordinated a brainstorming event to determine the best strategy to meet the product release date. After the project overview, the subject matter expert (SME) remained quiet during the call. What should the project manager do next?
- ✓ Correct A.Pose direct questions to the participants based on their area of expertise to start engaging them in the conversation.
- B.Cancel the meeting if team members do not have the skills to suggest a strategy.
- C.Create a strategy based on the project manager ' s experience and get approval during the call.
- D.Review the roles and responsibilities during the call to determine who is accountable for the strategy.
Correct answer: A
Explanation
The correct answer is A. Pose direct questions to the participants based on their area of expertise to start engaging them in the conversation. This approach follows project management best practices by addressing the situation effectively while maintaining proper processes and stakeholder alignment.