PMP Practice Question 1701 - People

PeopleResourcesTeamAgile

A project manager schedules virtual daily standup meetings for a project, but half of the team members regularly join late or miss the meeting altogether. What should the project manager do?

  • A.Use one-to-one virtual meetings because they are more efficient.
  • B.Ask senior management for coaching regarding this situation.
  • ✓ Correct C.Agree on a new time and reschedule the daily standups.
  • D.Discuss ground rules with the team that will include daily meetings.

Correct answer: C

Explanation

When half the team regularly joins late or misses daily standup meetings, the project manager should agree on a new time and reschedule the standups. Finding a time that works for all team members ensures participation and maintains the meeting's value for alignment and feedback. Using one-to-one meetings instead (A) loses the team-wide visibility benefit. Asking management for coaching (B) does not directly solve the scheduling issue. Discussing ground rules (D) addresses behavior but may not resolve underlying scheduling conflicts.

Practice the full 2,250-question bank

This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.

Start free