PMP Practice Question 2038 - Process

ProcessGovernanceMeasurementAgile

A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative. What should the project manager do next?

  • A.Document lessons learned before closing.
  • B.Consult the project charter for next steps.
  • ✓ Correct C.Confirm the definition of done (DoD) has been met.
  • D.Review organizational process assets (OPAs) for clarity.

Correct answer: C

Explanation

When a project is nearing completion and the sponsor is asking about the PM's next assignment, the project manager should first confirm that the definition of done has been met. Verifying completeness before closure is essential. Documenting lessons learned (A) is part of closure but comes after confirming DoD. Consulting the charter (B) is not the next step at closure. Reviewing OPAs (D) is organizational, not project-specific.

Practice the full 2,250-question bank

This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.

Start free