PMP Practice Question 2063 - Process
A project team has finished participating in an iterative product increment planning session. After the planning session, the team returns with a list of features to deliver. How should the project manager ensure the product increments deliver the anticipated requirements?
- A.Appoint a dedicated product manager for the duration of the release
- B.Track business outcomes for planned user stories.
- ✓ Correct C.Ensure every user story has acceptance criteria.
- D.Have the customer approve the product increment features.
Correct answer: C
Explanation
After an iterative planning session produces a feature list, the project manager should ensure every user story has acceptance criteria to verify anticipated requirements are delivered. Acceptance criteria define done for each story. Appointing a product manager (A) creates a new role unnecessarily. Tracking business outcomes (B) is valuable but secondary to defining acceptance criteria. Having the customer approve features (D) is part of acceptance but not the primary mechanism.
Practice the full 2,250-question bank
This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.
Start free