PMP Practice Question 2101 - People

PeopleStakeholdersAgile

A project manager is leading a complex project. The project stakeholders include individuals from different countries, cultures, and languages. What can the project manager do to manage this diverse group of stakeholders?

  • A.Establish one language as the main language for communications and an official time zone for the project.
  • ✓ Correct B.Perform an analysis to better understand the communication needs and preferences of 1297 each group.
  • C.Organize and assign the team members to the project deliverables according to their cultures and languages.
  • D.Ask the project management office (PMO) to assign a cultural manager to oversee relations between diverse groups.

Correct answer: B

Explanation

When managing stakeholders from different countries, cultures, and languages, the project manager should perform an analysis to understand communication needs and preferences of each group. Tailored communication improves engagement. Establishing one language and time zone (A) is rigid. Assigning by culture and language (C) is inappropriate. Requesting a cultural manager from the PMO (D) adds unnecessary overhead.