A project manager has recently been appointed to lead a critical software development project in a hybrid environment. What should the project manager do first to understand the project quickly and manage the project effectively?

  • A.Assess the project management plan for dependencies and possible risks then validate stakeholder understanding.
  • B.Share project objectives and scope with the team to ensure it understands the project value.
  • ✓ Correct C.Review the project charter to understand the objectives, high-level scope, and business need.
  • D.Identify key stakeholders and hold a project kickoff meeting to engage the stakeholders and obtain commitment.

Correct answer: C

Explanation

When newly appointed to lead a critical hybrid software project, the project manager should first review the project charter to understand the objectives, high-level scope, and business need. The charter provides foundational context for all subsequent activities and decisions. Assessing the project management plan (A) is detailed and time-consuming without charter context. Sharing objectives with the team (B) should follow charter review. Holding a kickoff meeting (D) is most effective after the PM understands the charter.