PMP Practice Question 226 - Process
A project just kicked off and management's expectation is to ensure that the deliverable of the first iteration helps the marketing team present the product prototype to potential customers. What should the project manager do?
- A.Ask the sponsor to prioritize some functionalities of the product.
- B.Split the backlog into phases to ensure that the key features are delivered first
- C.Increase the details of the work breakdown structure (WBS) to minimize errors and delays .
- ✓ Correct D.Identify the minimum functionality required for the product
Correct answer: D
Explanation
The PM should identify the minimum functionality required for the product—the minimum viable product (MVP). An MVP delivers enough features to satisfy early customers and generate feedback for future development. By collaborating with the sponsor, marketing team, and customers to understand core needs, the PM can focus the first iteration on the features that provide the most value. This approach reduces scope, cost, and time while maximizing quality and customer satisfaction.