PMP Practice Question 251 - Process
A project was initiated due to an external business influence. During the course of the project, some of the business parameters considered at the beginning of the project have changed. What should the project manager do?
- ✓ Correct A.Request management to update the project requirements accordingly.
- B.Inform management that the agreed-upon scope cannot be changed.
- C.Inform the team not to accept any changes, as it involves significant rework.
- D.Request an update of only new requirements, as other changes involve rework.
Correct answer: A
Explanation
When external business influences change parameters considered at project initiation, the project manager should request management to update project requirements accordingly. Adapting to changing business conditions maintains project relevance. Informing management scope cannot change (B) is rigid. Not accepting changes due to rework (C) ignores business needs. Requesting only new requirements (D) creates an incomplete picture.
Practice the full 2,250-question bank
This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.
Start free