PMP Practice Question 288 - People
An important national project is in the execution phase. A time-constraint activity must be conducted on-site by a specialist from another country. Due to travel restrictions, the specialist cannot perform the activity on-site. The activity cannot be completed without the specialist's expertise. The project team is actively seeking assistance in order to complete the job on time. What should the project manager do to help the project team?
- A.Seek additional budget to train the project team on the required skill set.
- B.Refer to the organization ' s lessons learned repository and find an alternative solution.
- C.Reschedule the project until the local travel restrictions are lifted.
- ✓ Correct D.Schedule virtual sessions with the specialist to guide the team in completing the activity.
Correct answer: D
Explanation
When a specialist cannot travel on-site due to restrictions for a time-constrained activity, the project manager should schedule virtual sessions with the specialist to guide the team in completing the activity. Virtual collaboration maintains progress within time constraints. Seeking budget for team training (A) takes too long. Referring to lessons learned (B) may not provide the specific expertise needed. Rescheduling until restrictions lift (C) causes unacceptable delay.