PMP Practice Question 238 - Business Environment

Business EnvironmentRiskProcessUncertaintyGeneral

A project manager for a software development company faces a number of financial risks in their project. The project manager needs to frequently check the strength and efficiency of the risk management process. What should the project manager use to accomplish this?

  • A.Stakeholder register
  • B.Brainstorming session
  • C.Assumption log
  • ✓ Correct D.Audit meeting

Correct answer: D

Explanation

Audit meetings provide a systematic, independent, and documented evaluation of risk management process effectiveness. They assess whether risk management criteria are being met, identify improvement areas, and ensure the process remains robust and adaptable. Regular audits are essential for maintaining the strength and relevance of risk management practices as project conditions evolve.

Practice the full 2,250-question bank

This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.

Start free