A project is approaching successful completion, and all stakeholders are really proud of the achieved results. The project management office (PMO) recommends the project manager to lead the next similar project. What should the project manager do next?

  • ✓ Correct A.Engage key stakeholders to complete and deliver lessons learned.
  • B.Present the project achievements and delegate knowledge transfer to the steering committee.
  • C.Request the PMO to manage the lessons learned repository.
  • D.Select the same stakeholders for the next project to avoid doing knowledge transfer.

Correct answer: A

Explanation

When a project approaches successful completion and the PMO recommends the PM lead the next similar project, the project manager should engage key stakeholders to complete and deliver lessons learned. Capturing insights while they are fresh ensures the organization benefits from this project's experience. Presenting achievements and delegating knowledge transfer (B) shifts responsibility. Requesting the PMO manage the repository (C) is administrative. Selecting the same stakeholders for the next project (D) avoids knowledge transfer.