PMP Practice Question 776 - Business Environment
Two days before the end of a sprint, a team member updates the team lead that they will not be able to complete their tasks for the sprint due to a technical difficulty. What should the agile team lead do?
- ✓ Correct A.Raise this issue during the daily meeting to determine a possible solution with the team.
- B.Suggest the team member get more technical training in the next quarter. 1283
- C.Inform the product owner of the issue and request that they reprioritize the delayed task.
- D.Update the risk register to reflect the possible risk of a schedule delay.
Correct answer: A
Explanation
When a team member cannot complete sprint tasks due to a technical difficulty two days before sprint end, the agile team lead should raise the issue during the daily meeting to determine a solution with the team. Team collaboration enables swarming. Suggesting training (B) does not address the current sprint. Informing the PO to reprioritize (C) may follow but team problem-solving comes first. Updating the risk register (D) is a predictive practice.