PMP Practice Question 988 - People
A newly formed team has become accustomed to agile practices. The project lead has noticed that while they are performing according to expectations, there is boredom with daily team practices among many of the team members. What should the project lead do in this situation?
- A.Speak with individual team members to determine what they would like to do to improve the situation in the team 595
- B.Challenge the team to find new ways to achieve higher levels of performance to improve the situation.
- C.Have the team inform senior management of the situation and ask for recommendations.
- ✓ Correct D.Allow the team to self-organize and have them analyze the situation in their retrospective session and self correct
Correct answer: D
Explanation
When an agile team performs well but shows boredom with daily practices, the project lead should allow the team to self-organize and have them analyze the situation in their retrospective session and self-correct. Agile teams are expected to inspect and adapt their own processes. Speaking with individuals (A) bypasses team self-organization. Challenging the team to higher performance (B) does not address the boredom. Asking senior management for recommendations (C) undermines team autonomy.