PMP Practice Question 1001 - People
A project team has not been meeting its deliverables because they are not receiving adequate resources to do their job. What should the project manager do for the team to meet the upcoming deliverables?
- A.Ask the team to adapt based on their current resources.
- B.Replan the upcoming deliverables based on the available tools.
- C.Plan a meeting with the stakeholders to get more resources.
- ✓ Correct D.Ask the project sponsor to provide the needed resources.
Correct answer: D
Explanation
The PM should request the project sponsor to provide needed resources. Effective resource management ensures team members have the necessary skills, tools, and support. When resource gaps are identified, the PM should escalate to the appropriate authority for resolution rather than attempting workarounds that compromise project quality or team performance.
Practice the full 2,250-question bank
This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.
Start free