PMP Practice Question 1813 - Process

ProcessResourcesPlanningAgile

A project has obtained all of the necessary legal requirements and policies from the local government. During the execution phase, the product owner is informed that a new law impacting the project deliverables will be published within two weeks. What should the project lead do?

  • A.Develop a change request for more resources and update the project budget and schedule.
  • ✓ Correct B.Review the product backlog items to evaluate the impact on scope and prioritize accordingly.
  • C.Work with the team to develop an alternative solution with no additional effect on the project ' s budget. 1178
  • D.Ask the internal legal department to evaluate if the regulatory law could be managed internally.

Correct answer: B

Explanation

When a new law impacting deliverables will be published within two weeks during execution, the project lead should review product backlog items to evaluate the impact on scope and prioritize accordingly. Backlog assessment ensures agile adaptation to regulatory change. Developing a change request for resources (A) assumes resource needs before impact analysis. Working on alternative solutions with no budget impact (C) constrains options prematurely. Asking legal to evaluate (D) may supplement but is not the first step.