PMP Practice Question 38 - People
A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches. What does the project manager need to do first in order to have good project performance?
- A.Deliver hybrid training to all team members
- ✓ Correct B.Assess the required training per team member.
- C.Coach those team members lacking hybrid knowledge to learn on the job.
- D.Change the team to include hybrid experts
Correct answer: B
Explanation
When starting a hybrid project and some team members only have predictive knowledge, the project manager should first assess the required training per team member. This assessment identifies individual knowledge gaps and skills needs relative to the hybrid approach, enabling targeted and efficient training plans. Delivering broad hybrid training to everyone (A) may be inefficient if some already have the needed skills. Coaching on the job without assessment (C) lacks structure and may miss critical gaps. Changing the team to include hybrid experts (D) replaces team members rather than developing existing ones.
Practice the full 2,250-question bank
This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.
Start free