PMP Practice Question 51 - People

PeopleResourcesTeamHybrid

An agile project manager notices that one of the team members is developing extensive knowledge in a specific matter. Other team members are likely to require this knowledge in the future. What should the agile project manager do?

  • A.Ask the team member to record highlights the team may want to know.
  • ✓ Correct B.Ask the team member to provide a training session for the rest of the team.
  • C.Ask the team member to produce a lessons learned document and share it with the team.
  • D.Ask the team member to develop more expertise and become a subject matter expert (SME).

Correct answer: B

Explanation

When an agile team member develops extensive specialized knowledge that others will need, the project manager should ask the team member to provide a training session for the rest of the team. This promotes knowledge sharing, collaboration, and team resilience. Asking them to record highlights (A) is passive. Asking them to create a lessons learned document (C) is retrospective rather than proactive. Encouraging further expertise development (D) does not address the team's knowledge gap.