PMP Practice Question 901 - Process
A project team consists of several consultants from an external vendor. These consultants often change from month to month. What should the project manager do to communicate the organizational values?
- A.Host a question and answer (Q & A) session with the new team members.
- ✓ Correct B.Distribute the team charter to new team members.
- C.Review communications options with the vendor.
- D.Schedule a collaborative team outing to strengthen team relationships.
Correct answer: B
Explanation
The correct answer is B. Distribute the team charter to new team members. Effective communication considers cultural differences, stakeholder preferences, and the appropriate format for information exchange. The PM should tailor communication approaches to the audience.