PMP Practice Question 913 - People

PeopleFinanceTeamAgile

A project team is experiencing conflict between two team members. Team member A feels that team member B is always talking over team member A and does not listen to any advice. Team member B is not willing to listen to feedback. What should the project manager do to resolve the issue?

  • A.Report the performance issue to both of the team members ' supervisors
  • B.Move one of the team members to a different protect team
  • C.Modify the communications management plan and resend it to the team
  • ✓ Correct D.Review the ground rules for collaboration within the team

Correct answer: D

Explanation

When team member A feels talked over and team member B will not listen to feedback, the project manager should review the ground rules for collaboration within the team. Reinforcing norms addresses behavioral expectations. Reporting to supervisors (A) escalates unnecessarily. Moving a team member (B) avoids resolution. Modifying the communications plan (C) addresses documents, not interpersonal behavior.

Practice the full 2,250-question bank

This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.

Start free