PMP Practice Question 926 - People

PeopleResourcesTeamGeneral

At the end of a meeting, a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project. What should the project manager do in this situation?

  • ✓ Correct A.Ask the functional manager to create a specific responsible, accountable, consult, and inform (RACI) chart for the team member
  • B.Develop a work plan for the project team member with the help of the resource manager
  • C.Tell the functional manager and the project team member to review the projectcharter
  • D.Advise the functional manager and the project team member to review the resource management plan

Correct answer: A

Explanation

When a functional manager raises concerns about a team member unclear on their role and responsibilities, the project manager should ask the functional manager to create a specific RACI chart for the team member. A RACI chart clarifies involvement levels for each activity. Developing a work plan with the resource manager (B) addresses tasks, not role clarity. Reviewing the project charter (C) is too high-level. Reviewing the resource management plan (D) may not provide activity-level role definition.

Practice the full 2,250-question bank

This page is a free public sample. Sign up to save your progress, build a wrong-answer notebook, and track accuracy by domain - free for 7 days.

Start free